2) If we cancel the building inspection due to non-compliance with safety issues, will the remaining fee not be paid? (Alireza Lashgari)
3) Under the demolished building, there is an old water tank with dimensions of 4×3 and depth of 2 meters, which is filled with soil. Now, to implement the foundation of the new building (4-story residential), what materials should we fill this reservoir with? Please give the exact materials and details of their use. (Civil Engineer)
4) A: Regarding concrete and rebar tests, the number of tests, laboratories approved by the Ministry of Roads and Urban Development of Tehran.
b) The relationship between the supervisor and the engineering and executive system and the manufacturer and the concrete and rebar laboratories?
Q: Can you explain more about concrete in Tehran?
T: What are the full duties of the supervisor regarding concrete, concreting and concrete tests, concrete laboratories?
S: Introduce a suitable training file for monitoring so that everyone can use it and serve the construction community. (Ibrahim Arkand)
5) I supervised the work of designing a guard structure for him. What if I run the building guard without the structure and the system will understand and get stuck? There are several mistakes in the structural and architectural plan, such as not having the size of the torsion bars of the stairwell. Should I fix it myself or should the designer order it? Do you want to change the map? What should I do?
(Nader Etamadi)
6) A: Regarding the new wall post system, does connecting the packages with the Hilti gun contradict the provisions of Appendix 6?
B: Is there a possibility of the galvanized profile falling out of place and inside the packages in the new wall post system?
c) What are the advantages and disadvantages of working with rabbits in false ceilings and which ones are more economical in terms of cost and operation?
T: There is no legal problem with the under-ceiling water and sewage system instead of passing through the floor, especially during repairs? (Shams Burhan)
6) What is the supervisor’s responsibility for concrete testing? Finally, to whom should it be delivered? (Bidi leaf siam)
7) A: The owner is not looking for a finisher, there are some defects in the implementation. The building is in use. Can I reject the construction completion report to get my fee?
B: In the staged report, it was reported that the wall post was not implemented, now the owner has come and says to do it for the finish. Can you do something? (Reza Tapak)
8) Hello, the concrete that the laboratory takes for testing, when should we get the answer and should we keep the answer as part of the monitoring documents or not? (Masoud)
9) Is the delivery of phased reports to the licensing authorities with the coordinator supervisor only? (Mohammed Kermani)
10) Explain about the interpretation of concrete results? (Muhammad)
11) When approving the thesis, what order is required for the person who executed the second plan? (Mr. Hashem Begi)
12) Which supervisor is in charge of controlling the scope of Sang Nama? (Mustafa)
13) A: Description of the structure supervisor’s duties in monitoring the roof of metal and concrete buildings
B: Who is concerned with the safety of the team of employees during work and what arrangements should be made? (ar.ya451)
14) If the administrator of the security structure has not implemented, how should we write the report so that it does not harm us later? (Arzoo Ahadzadeh)
15) A: The difference between building design systems, such as bending frame and )
B: Foundation molding time? (Goddess of Shabani)