Abadan municipality’s inattention to the report of supervising engineers, the cause of the “Metropole” building accident. According to Fars news agency from Abadan, Hamzeh Shakib, head of the country’s engineering system organization, said in a group of reporters, referring to the accident of the Abadan Metropole building: “Abadan municipality to the reports of the engineering system organization” He did not pay attention to the construction status of this project. According to the preliminary report and the current information that needs to be completed, the Metropol building received a construction permit in 2016, but the design of the building was not done by the engineering organization.
After the representative office of the engineering organization in Abadan noticed the construction of this tower, it entered and the contractor was forced to choose the supervising engineer.
Supervising engineers have regularly controlled the construction process and reported the critical status of the project; Even in its last report, which is related to 1401, the critical status of the project was once again reported to the municipality, but the report of the engineering organization was not paid attention to.
The engineering system organization does not have the legal duty and the means to stop the project, the engineering system organization can only report the violations to the municipality during the construction process, and the municipality must stop the unauthorized construction.
In an obvious violation, 3 floors of this tower were built as an addition, and ignoring the report of the supervising engineers led to this disaster.
This incident should be a lesson to follow the national building regulations. Join us: @Madeh_33