According to the letter issued by the Ministry of Roads and Urban Development No. 153176/430 dated 9/11/1400, the supervisor must prepare and deliver a written warning to the executive according to the clauses mentioned in the text of the letter.

The written notice to the presenter includes three parts:
#First_Part: Property information

Mr. Engineer or (respectable managing director of the company. Mr. Engineer.) Respected executor of the registration plate.
During the visit made on / /
From the above license plate to the address. With building permit No., I, the engineer (inspector) of the said license plate, hereby inform you of the following details.

#Second_Part: Statement of things that should be observed or corrected (as an example)

1- Before starting the construction operation, the contractor is obliged to carry out the following measures according to section 12-1-4 of the twelfth topic:
Civil and third-party liability insurance for the workshop, as well as compulsory insurance for construction workers, should be established.
Disconnecting or moving the branching of water, electricity, gas and other infrastructure facilities before demolition and excavation

2- According to Article 21 of the Code of Conduct for the Protection of Construction Sites, before starting construction operations in the vicinity of low voltage overhead power lines, the relevant authorities and authorities must be notified in order to take necessary precautionary measures, such as cutting off current, temporarily or permanently changing the route or cover. Lines adjacent to the building should be done with appropriate materials such as polyethylene pipes or rubber hoses, etc.

3-According to Article 34 of the Code of Conduct for the Protection of Construction Workshops, the movement path and location of cranes and other lifting devices must be visited and checked to the exact length beforehand, so that during movement and work, there is no danger through contact with electric wires and cables or facilities and buildings. Existing or falling in excavated places, etc., do not notice the operator, workers and other people.

4- According to Article 192 of the Regulations for the Protection of Construction Workshops, the operator is obliged to carefully inspect all the parts of the building under demolition before starting the demolition operation, and if there are dangerous and collapsible parts, take precautionary measures such as installing Piles, shields and buffers and temporary columns should be used to restrain that part.

#third_part: the final part

It is obvious that in case of non-implementation and observance of the mentioned items, all legal, civil and criminal responsibilities, as well as financial and personal consequences resulting from the non-implementation of these items, are the responsibility of the executor.
This written communication in page and The paragraph was prepared and explained to the executive, notified and delivered.

Let the engineers know

Respected observers should note: written notification to the moderator does not relieve your responsibility and it is necessary according to #paragraph 2_5_3 of the second discussion
Whenever supervisors come across a violation during implementation, they must report the case to the building permit issuing authority and the construction engineering system organization of the province.

#Example of written notice to the presenter